Halwatura Ganga Mini Hydro Plant


The project under Terraqua International Pvt. Ltd. was commissioned in February 2009 and has an installed capacity of 1.3MW. The project is a fully owned subsidiary of RENEWGEN (Pvt) Ltd., and is managed by Diyaviduli (Pvt) Ltd.

Location
Uda Malibada, Deraniyagala

Technical Specification
Plant Capacity 1.3MW
Design Flow 0.8 m3/sec
Net Head 185m
Turbine Type Pelton
Generator 1500kVA
Power House Open air type right bank
Plant Factor 45%
Transformer Type 33/0.690kV, 1, 650kVA Indoor